MS Project calculates the Finish Date of a task from the Actual Start plus Duration and it ignores the Remaining Duration, the Current Date and the Status Date. It’s not possible in Microsoft Project to unlink the Remaining Duration and %Complete.Ģ. When we get down to the details of why MS Project isn’t right, it boils down to two common issues:ġ. Quite often I hear from our construction clients that the typical Primavera is the “right” tool for scheduling construction projects and that MS Project is not “right”. Posted by: Laith Adel on December 11, 2014